How long does it take to build an app? What decides it
How long does it take to build an app? It depends on six things you can check before a quote: scope, user roles, integrations, design, store review, feedback.
EK Ra Sunya team
EK Ra Sunya Inc.
How long it takes to build an app depends less on the code than on six things you can check before anyone quotes: how clear the scope is, how many kinds of user the app serves, how many outside systems it talks to, how much custom design it needs, how the app stores treat your account, and how quickly you answer questions during the build. Anyone who gives you a firm date before those six are known is guessing.
That's why this post has no "a simple app takes X months" table. Those tables can't know your app. What follows is what moves the schedule, and how to get a date you can plan around.
What decides how long an app takes to build?
Think of the schedule as the sum of decisions, some of which you control.
| Factor | Pushes the schedule out when | You can shorten it by |
|---|---|---|
| Scope clarity | Features are described in one line, or still being decided | Writing down each screen and what it does |
| User roles | Customers, staff, managers and admins each need their own screens and permissions | Starting with the roles you need on day one |
| Integrations | Payments, maps, an existing ERP or a government API are involved | Getting access and documentation early |
| Design | Every screen is custom, with animation and brand work | Using a proven component set for back-office screens |
| Store review | The account is new, the submission is incomplete, or the app needs a login | Preparing accounts, test logins and policies ahead |
| Feedback speed | Answers and approvals take days to come back | Naming one decision-maker with time set aside |
None of these is about how fast developers type. Most delays happen between pieces of work, while someone waits for a decision, a login or a document.
Why does scope clarity matter more than app size?
A short feature list can hide a long build. "Customers can book an appointment" might mean one screen with a date picker. It might also mean staff calendars, holidays, reminders, cancellations, deposits and a report for the owner. Both fit in one line of a brief.
The fix is to describe each feature well enough that two people would build the same thing. Our guide to what to prepare before asking for a quote walks through it. A clear brief doesn't only make the estimate more accurate. It also cuts the back-and-forth during the build, which is where much of the calendar goes.
Scope that changes mid-build moves the date too, and that's fine as long as everyone sees it happen. At EK Ra Sunya, a change request follows a written request, then a time and cost estimate, then the client's approval before any of it is built. So the schedule effect is visible before anyone commits to it. Our post on change requests in fixed-price projects explains how that works.
How do user roles and integrations change the timeline?
Every role multiplies work. A delivery app for customers is one app. Add riders, restaurant staff and an admin panel, and you have four sets of screens, four sets of permissions and four groups to test with. Ask which roles must exist on launch day. Often the admin side can start as a simple web panel and grow later.
Integrations carry a different kind of risk, because part of the schedule belongs to someone else. A payment gateway needs a merchant account. A link to your existing accounting or ERP system needs credentials, documentation and a person on that side who answers questions. If any of those take a while, the integration waits, however ready the app is. Start those requests the week you decide to build, not when the developer asks.
How long do Apple and Google take to review an app?
This is the one part of the timeline where the platforms publish their own numbers.
Apple says on its App Review page that it typically reviews at least 50% of submissions in less than 24 hours and 90% in less than 48 hours. The same page warns that incomplete submissions may be delayed or may not pass. A rejection means fixing the issue and submitting again, so the realistic risk is the round trip, not the first review.
Google's publishing help page says that for certain developer accounts, review can take up to seven days, or longer in exceptional cases. There is also a rule that catches new accounts. Personal Play Console accounts created after 13 November 2023 must run a closed test with at least 12 testers who stay opted in for at least 14 days before they can apply for production access.
Before either store sees the app, the developer accounts have to exist, and account setup has its own steps. For Apple, see opening an Apple developer account from Nepal. Put all of this on the plan as its own line, separate from development.
Why does your feedback speed change the date?
Because a build is a conversation. Developers show a screen, you say what's wrong with it, they change it. If each answer takes a week, every loop takes a week, and a project with dozens of loops drifts by months without anyone doing anything wrong.
Three habits help:
- One decision-maker. Feedback from five people who disagree has to be reconciled before anyone can act on it.
- A regular slot. A fixed weekly review keeps questions from piling up.
- Test as you go. Acceptance testing at the end finds everything at once. Our user acceptance testing checklist works for each finished feature, not only for launch.
Holidays matter too, on both sides. EK Ra Sunya shares its office closure dates, such as Dashain and Tihar, with clients at the start of each year and of each new project, so both sides can plan around them. Ask any team you hire for the same.
How do you get a realistic schedule?
Ask for the estimate in a form you can test:
- Broken down by feature, so you can see what each one costs in time and drop or defer the expensive ones.
- With assumptions written out. "Assumes the payment merchant account is ready" is a dependency you can work on today.
- With store review and testing as separate lines, not folded into development.
- With your own tasks listed: content, logins, approvals, test devices, testers.
Then ask what happens to the date if one assumption breaks. A team that has thought about it will answer straight away. Be wary of a date that arrives fast, with no questions about roles, integrations or who approves the work.
Frequently asked questions
Can an app be built faster by adding more developers?
Sometimes, for work that splits cleanly, such as an admin panel and a customer app. It does nothing for time lost waiting on decisions, third-party access or store review, and no extra developer can speed those up.
Does building for both iOS and Android double the time?
Not with a cross-platform framework such as Flutter or React Native, where one codebase serves both. Each store still needs its own account, listing and review, so plan those separately.
Can Apple review be sped up?
Apple accepts requests for an expedited review in specific cases, such as fixing a critical bug or launching to coincide with an event your app is directly tied to. It isn't a way to skip review for a normal launch.
When should we set a launch date?
After the scope is written down, the integrations have access confirmed and the store accounts exist. Before that, any date is a target, not a schedule.
Planning your app
Our mobile development team builds Flutter and React Native apps and takes them through both stores. If you want an estimate broken down the way this post describes, tell us about the app.
Have a project in mind?
Let us help you build something scalable, fast, and built to last.
Start a conversationKeep reading
Payment gateway integration in Nepal: eSewa, Khalti and more
Payment gateway integration in Nepal, step by step: merchant account, sandbox testing, server-side verification, pending payments, refunds and reconciliation.
BusinessSwitch software development company without losing your app
How to switch software development company mid-project or after launch: what to collect first, how to ask for the handover, and what the new team does first.